1606 Jones St
San Francisco permit 202310058134 · Nob Hill
To comply with dbi internal audit nov 202306395 where work was done under canceled permit #201812067678. this permit to legalize one adu at basement level with one bedroom per state adu ordinance
- Filed
- Oct 5, 2023
- Issued
- Jun 17, 2024 (8 months after filing)
- Completed
- Oct 22, 2024 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 49 stops across 5 departments
- Comments issued
- 14 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 5, 2023 | Oct 30, 2023 | Administrative |
Code enforcement Building Inspection · CES | Oct 20, 2023 | Oct 20, 2023 | — |
Building inspector Building Inspection · BID-INSP | Oct 25, 2023 | Oct 25, 2023 | Approved |
Apartment and hotel inspection Building Inspection · HIS | Oct 26, 2023 | Oct 26, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 30, 2023 | Nov 9, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 30, 2023 | Dec 15, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2023 | Nov 21, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 30, 2023 | Dec 18, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2023 | Nov 1, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 30, 2023 | Dec 5, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 30, 2023 | Nov 3, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 30, 2023 | May 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 18, 2024 | Jan 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 18, 2024 | Jan 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 18, 2024 | Jan 19, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 18, 2024 | Jan 22, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 18, 2024 | Jan 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 18, 2024 | Jan 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 18, 2024 | Jan 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2024 | Mar 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 20, 2024 | Mar 21, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 20, 2024 | Mar 28, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 20, 2024 | Mar 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 20, 2024 | Apr 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2024 | Mar 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 20, 2024 | Mar 25, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 10, 2024 | Apr 17, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 10, 2024 | Apr 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2024 | Apr 15, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 10, 2024 | Apr 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2024 | Apr 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2024 | Apr 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2024 | Apr 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2024 | Apr 10, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 18, 2024 | Apr 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 18, 2024 | Apr 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 18, 2024 | Apr 18, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2024 | Apr 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 18, 2024 | Apr 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 18, 2024 | Apr 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 1, 2024 | May 17, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | May 1, 2024 | May 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 1, 2024 | May 7, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 1, 2024 | May 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 1, 2024 | May 13, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | May 1, 2024 | May 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2024 | May 2, 2024 | Approved |
Development fee collection Building Inspection · DFCU | May 20, 2024 | May 20, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 21, 2024 | Jun 17, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $158,452
| Name | Role | License on permit |
|---|---|---|
| Michael Bernard Harris Michael Harris Architecture | Architect | C15349 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025