360 03rd St
San Francisco permit 202310068165 · South of Market
Replace (2) 80 ton air-cooled chillers on roof along with three chillers water pumps. no work in the interior of the building.
- Filed
- Oct 6, 2023
- Issued
- Oct 20, 2023 (within 1 month of filing)
- Completed
- Oct 8, 2024 (12 months after issuance)
- Review stops
- 9 stops across 4 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 6, 2023 | Oct 6, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 6, 2023 | Oct 6, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 6, 2023 | Oct 6, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2023 | Oct 6, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 6, 2023 | Oct 6, 2023 | Approved |
Public health review Public Health · HEALTH | Oct 6, 2023 | Oct 6, 2023 | Administrative |
Intake Building Inspection · INTAKE | Oct 20, 2023 | Oct 20, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 20, 2023 | Oct 20, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2023 | Oct 20, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Carl Milsum | Engineer | S6190 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026