2500 Broadway
San Francisco permit 202310068212 · Pacific Heights
Full int remodel, infill under (e) deck. below grade expansion of north garage. change of exterior stair. minor ext changes- railing, windows, doors. structural upgrade, earth shoring for garage expansion
- Filed
- May 8, 2024
- Issued
- Jun 2, 2025 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 33 stops across 6 departments
- Comments issued
- 10 times, by Public Works, Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 6, 2023 | Oct 6, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 6, 2023 | Oct 6, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 13, 2023 | Oct 13, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 13, 2023 | Oct 13, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 29, 2023 | Nov 29, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 6, 2024 | Mar 6, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 11, 2024 | Apr 19, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 12, 2024 | Apr 12, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 17, 2024 | Apr 17, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 18, 2024 | Apr 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 23, 2024 | May 9, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 9, 2024 | May 21, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 9, 2024 | Jun 28, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 9, 2024 | Jun 17, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 9, 2024 | May 14, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 9, 2024 | May 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2024 | May 10, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 9, 2024 | May 20, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 9, 2024 | Sep 10, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 9, 2024 | Oct 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2025 | Mar 6, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 7, 2025 | Mar 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2025 | Mar 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2025 | Mar 11, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 27, 2025 | Mar 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 18, 2025 | Apr 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | Apr 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2025 | May 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2025 | May 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 13, 2025 | May 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2025 | May 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 16, 2025 | May 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 20, 2025 | Jun 2, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,000,000
| Name | Role | License on permit |
|---|---|---|
| Geddes J Ulinskas Geddes Ulinskas Arch. | Architect | C27862 |
| Stephen Sedgwick Sutro Sutro Architects | Architect | C30702 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022