215 Fremont St
San Francisco permit 202310108255 · Financial District/South Beach
4/f: ti (n) partition for proj work & utility rms. no change of use. all egress & life safety systems to remain in operation during & after construction. gc to provide temp exit signs/strobes as req by construction. no hazmat used/stored on site in limited qty.
- Filed
- Oct 10, 2023
- Issued
- Dec 12, 2023 (2 months after filing)
- Completed
- Jul 24, 2024 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 9 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 10, 2023 | Oct 10, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 10, 2023 | Oct 10, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 10, 2023 | Oct 10, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 10, 2023 | Oct 10, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2023 | Oct 10, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Oct 10, 2023 | Oct 10, 2023 | — |
Fire prevention review Fire Department · SFFD | Oct 11, 2023 | Dec 11, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 11, 2023 | Dec 11, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 11, 2023 | Dec 12, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $2,200,000
| Name | Role | License on permit |
|---|---|---|
| Wendy H Woo | Architect | C31772 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026