As written on the permit application.

Selective demo in suites 220,212, and 207 to accomdate the proposed tenant improvements. converting (e) consult room and (e) offices in suite 220 to 3 exam rooms, 1 exam/treatment room. remodel (e) suite 212 to 5 neuropsych offices, and admin. modify (e) hvac, plumbing, and electrial systems.

Timeline
Key dates from the city record.
Filed
Oct 12, 2023
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
18 stops across 5 departments
Comments issued
4 times, by Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Oct 12, 2023Administrative

Building plan review

Building Inspection · BLDG

Oct 13, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Oct 20, 2023Issued Comments

Intake

Building Inspection · INTAKE

Nov 9, 2023Administrative

Zoning review

Planning · CP-ZOC

Nov 16, 2023Administrative

Building plan review

Building Inspection · BLDG

Nov 16, 2023Approved

Fire prevention review

Fire Department · SFFD

Nov 16, 2023Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Nov 16, 2023Approved

Public health review

Public Health · HEALTH

Nov 16, 2023Administrative

Structural plan approval

Building Inspection · PAD-STR

Nov 17, 2023Approved

Electrical plan review

Building Inspection · MECH-E

Nov 21, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Dec 6, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Dec 8, 2023Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jan 31, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 14, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Permit Processing Center

Building Inspection · PPC

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Filed
Estimated cost
$900,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Hugh T Cotter

Solus Architects, Inc.

ArchitectC-26523
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202310128571 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record