Interior renovation of the upper unit. no work at basement (lower unit). kitchen & two bathrm renovation. (e) deck to be modified. convert (e) powder rm to full bath at g/f. new insulation. replace (1) furnace to electric heat pump system. no change of use, area of conditioned space & height.

The building, before and after
As recorded on the permit.
FactBeforeAfter
Use2 family dwellingNo change
Units2No change
Stories2No change
Timeline
Key dates from the city record.
Filed
Oct 13, 2023
Issued
Jul 14, 2025 (21 months after filing)
Completed
Aug 17, 2026 (13 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
12 stops across 3 departments
Comments issued
Twice, by Planning, Building Inspection
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 20, 2023Administrative

Zoning review

Planning · CP-ZOC

Jan 16, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Dec 10, 2024Administrative

Zoning review

Planning · CP-ZOC

Oct 1, 2024Approved

Building plan review

Building Inspection · BLDG

Nov 8, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 17, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 3, 2024Approved

Building plan review

Building Inspection · BLDG

Dec 5, 2024Approved

Zoning review

Planning · CP-ZOC

Dec 3, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 10, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 6, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jul 14, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$140,500
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Wing Kin Lee

Wing Lee Architects

ArchitectC28929
Lou Xiao

Lx Engineering

EngineerS5130
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202310138629 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record