2460 Francisco St
San Francisco permit 202310138648 · Marina
Comply w/ nov #202312133. pa #8404861. no new work. legalize (e) condition: no deck flr access hatch, no exterior stair under (e) deck, (e) guardrail 76" high
- Filed
- Oct 13, 2023
- Issued
- Feb 26, 2024 (4 months after filing)
- Completed
- Jun 1, 2026 (27 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 12 stops across 3 departments
- Comments issued
- Once, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Oct 13, 2023 | Oct 13, 2023 | Administrative |
Intake Building Inspection · INTAKE | Oct 13, 2023 | Oct 13, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 30, 2023 | Oct 30, 2023 | Denied |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2023 | Nov 9, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Nov 8, 2023 | Nov 8, 2023 | — |
Zoning review Planning · CP-ZOC | Nov 9, 2023 | Jan 17, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 6, 2024 | Feb 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 7, 2024 | Feb 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2024 | Feb 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 16, 2024 | Feb 21, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 22, 2024 | Feb 22, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 22, 2024 | Feb 26, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Patric Darren Mcmurtrie Kohlmyer Designs | Architect | C29072 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019