3372 22nd St
San Francisco permit 202310168685 · Mission
To convert (e) commercial to residential, to provide a new residential unit at 3372 22nd street with a new deck area. work includes additional foundation and framing elements of 1st story and new, near-grade deck at rear of building, dmj 10/17/2023;
- Filed
- Oct 16, 2023
- Issued
- Feb 19, 2025 (16 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 10 times, by Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 16, 2023 | Oct 16, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 16, 2023 | Oct 16, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2023 | Oct 16, 2023 | Denied |
Permit Center Permit Center · PERMIT-CTR | Oct 16, 2023 | Oct 16, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | Oct 17, 2023 | Oct 17, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2023 | Oct 25, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 26, 2023 | Dec 12, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2023 | Feb 6, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 6, 2024 | Feb 15, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 15, 2024 | Feb 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 20, 2024 | Feb 29, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2024 | Mar 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 15, 2024 | Mar 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 24, 2024 | Oct 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 9, 2024 | Oct 15, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 21, 2024 | Oct 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 28, 2024 | Nov 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2024 | Nov 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 16, 2024 | Dec 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 25, 2024 | Jan 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 25, 2024 | Jan 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2025 | Jan 6, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 9, 2025 | Jan 13, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 21, 2025 | Jan 23, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 24, 2025 | Jan 24, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 24, 2025 | Feb 19, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $383,017
| Name | Role | License on permit |
|---|---|---|
| Carlos Renan Dominguez Dominguez Associates | Engineer | C26949 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022