2380 Franklin St #0
San Francisco permit 202310178770 · Pacific Heights
Legalize 2nd unit at ground floor to jadu. add 2nd parking in (e) basement & reinforce foundation. add bedroom to 4th floor. add an elevator,doors & windows in the basement & 1st fl on th west elevation. new color for exterior,provide plu & elec.
- Filed
- Oct 17, 2023
- Issued
- Jan 2, 2025 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 33 stops across 5 departments
- Comments issued
- 11 times, by Planning, Building Inspection, Public Works, Public Utilities, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 17, 2023 | Oct 23, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 23, 2023 | Feb 13, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 23, 2023 | Dec 30, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 30, 2024 | May 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 31, 2024 | Jul 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 31, 2024 | Jul 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 31, 2024 | Jun 7, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 31, 2024 | Jun 5, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 24, 2024 | Jun 24, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2024 | Jul 15, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Jul 17, 2024 | Jul 17, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2024 | Jul 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Sep 4, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2024 | Sep 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Oct 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2024 | Oct 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 27, 2024 | Oct 3, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 30, 2024 | Sep 30, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 8, 2024 | Oct 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 11, 2024 | Nov 1, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 11, 2024 | Oct 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 11, 2024 | Dec 3, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 11, 2024 | Oct 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2024 | Oct 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Dec 3, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 3, 2024 | Dec 9, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 3, 2024 | Dec 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2024 | Dec 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 3, 2024 | Dec 10, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Dec 11, 2024 | Dec 11, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2024 | Jan 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 26, 2024 | Dec 26, 2024 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $900,000
| Name | Role | License on permit |
|---|---|---|
| Twen Ma Team Metric | Architect | C16815 |
| Francis Malkham Ace Pro Design | Engineer | C76860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025