1227 47th Av
San Francisco permit 202310188917 · Sunset/Parkside
Renovation (e) 2nd and 3rd levels. 0 sf added. new flat roof w/ deck at (e) 2nd fl roof. remove rear roof dormers and replace w/ pitch roof to match (e), new rear gable wall. new toilet and lav on 3rd lv, new laundry closet on 2nd level. replace roof. replace select
- Filed
- Oct 18, 2023
- Issued
- Jan 14, 2025 (15 months after filing)
- Completed
- Mar 25, 2026 (14 months after issuance)
- Review stops
- 22 stops across 4 departments
- Comments issued
- 5 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 18, 2023 | Oct 24, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 24, 2023 | Feb 27, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 24, 2023 | Dec 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 4, 2024 | Apr 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2024 | Jun 7, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 8, 2024 | May 3, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 8, 2024 | Apr 15, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 19, 2024 | Apr 24, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2024 | Jun 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2024 | Jun 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 5, 2024 | Jun 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 6, 2024 | Jun 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 6, 2024 | Jun 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 6, 2024 | Jun 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 6, 2024 | Jun 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Sep 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 20, 2024 | Nov 20, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 20, 2024 | Nov 21, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2024 | Dec 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2024 | Nov 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2024 | Dec 2, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 5, 2024 | Jan 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Richard A Merlau | Architect | C38697 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026