815 Joost Av
San Francisco permit 202310188924 · West of Twin Peaks
Re-plan layout of 1st & the lower fl. add total of (2) bedrm & (2) baths. add (n) family rm, (n) office lower fl. redesign illegal space lower fl to comply w/ regulations & increase living area. provide elec (n) equip, update elec meter from 100a to 200a. (n) plumb, ligthing, water heater, elec
- Filed
- Oct 18, 2023
- Issued
- May 20, 2024 (7 months after filing)
- Completed
- Nov 3, 2025 (17 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 8 times, by Planning, Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 18, 2023 | Oct 18, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 18, 2023 | Oct 18, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 18, 2023 | Oct 18, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 19, 2023 | Oct 19, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 6, 2023 | Nov 6, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 6, 2023 | Dec 28, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 6, 2023 | Jan 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2023 | Nov 28, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2023 | Nov 30, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 6, 2023 | Nov 6, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 6, 2023 | May 9, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2023 | Dec 15, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 18, 2023 | Dec 20, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 18, 2023 | Dec 18, 2023 | Approved |
Building plan review Building Inspection · BLDG | Feb 27, 2024 | Feb 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 28, 2024 | Feb 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | Mar 28, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 1, 2024 | May 2, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 1, 2024 | May 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 1, 2024 | May 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2024 | May 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 9, 2024 | May 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Francis Malkham | Engineer | C-76860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2008