San Francisco permit 202310188924 · West of Twin Peaks

Home remodel (type unconfirmed)Full plan reviewComplete
Street view · May 2008
Google Street View of 815 Joost Av, May 2008
Scope of work
As written on the permit application.

Re-plan layout of 1st & the lower fl. add total of (2) bedrm & (2) baths. add (n) family rm, (n) office lower fl. redesign illegal space lower fl to comply w/ regulations & increase living area. provide elec (n) equip, update elec meter from 100a to 200a. (n) plumb, ligthing, water heater, elec

Timeline
Key dates from the city record.
Filed
Oct 18, 2023
Issued
May 20, 2024 (7 months after filing)
Completed
Nov 3, 2025 (17 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 4 departments
Comments issued
8 times, by Planning, Building Inspection, Public Utilities
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Oct 18, 2023Administrative

Zoning review

Planning · CP-ZOC

Oct 18, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Oct 18, 2023Approved

Building plan review

Building Inspection · BLDG

Oct 19, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Nov 6, 2023Administrative

Building plan review

Building Inspection · BLDG

Dec 28, 2023Administrative

Building plan review

Building Inspection · BLDG

Jan 12, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 28, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 30, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Nov 6, 2023Issued Comments

Permit Processing Center

Building Inspection · PPC

May 9, 2024Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Dec 15, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 20, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Dec 18, 2023Approved

Building plan review

Building Inspection · BLDG

Feb 28, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 28, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Mar 28, 2024Approved

Fire prevention review

Fire Department · SFFD

May 2, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

May 6, 2024Approved

Zoning review

Planning · CP-ZOC

May 1, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 8, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 20, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$350,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Francis MalkhamEngineerC-76860
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202310188924 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record