472 Hazelwood Av
San Francisco permit 202310199055 · West of Twin Peaks
Reconstruction of existing foundations, addition of plywood to floor diaphragm and g/f walls, addition of 2 full bathrooms and 2 bedrooms. rebuild side steps. added drainage on property. horizontal excavation in basement.
- Filed
- Oct 19, 2023
- Issued
- Jun 11, 2024 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection, Public Utilities, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 19, 2023 | Oct 19, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 19, 2023 | Oct 19, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 19, 2023 | Oct 19, 2023 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 9, 2023 | Nov 9, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Nov 10, 2023 | Nov 14, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 14, 2023 | Jan 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 18, 2024 | Feb 22, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 22, 2024 | Jan 24, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2024 | Feb 23, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 26, 2024 | Mar 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 21, 2024 | May 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 3, 2024 | Apr 3, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Apr 3, 2024 | Apr 12, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 8, 2024 | Apr 10, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 15, 2024 | Apr 29, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 7, 2024 | May 8, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 14, 2024 | May 14, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2024 | May 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2024 | May 21, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 21, 2024 | May 24, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 24, 2024 | Jun 4, 2024 | Approved |
Building inspector Building Inspection · BID-INSP | Jun 4, 2024 | Jun 4, 2024 | — |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2024 | Jun 6, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 10, 2024 | Jun 10, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2024 | Jun 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $206,000
| Name | Role | License on permit |
|---|---|---|
| Akuavi Hine Murphy Brr Curry Inc | Engineer | S-6470 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025