1722 25th Av
San Francisco permit 202310209102 · Sunset/Parkside
This project is residential interior remodeling to existing two story house. proposed to convert garage space to family day-care less than 14 children (r-3 occupancy) on the first floor.
- Filed
- Oct 20, 2023
- Issued
- Oct 31, 2024 (12 months after filing)
- Completed
- Nov 4, 2025 (12 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 46 stops across 6 departments
- Comments issued
- 17 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 25, 2023 | Oct 27, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 27, 2023 | Dec 26, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 27, 2023 | Sep 20, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 7, 2024 | Feb 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 8, 2024 | Mar 12, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 8, 2024 | Mar 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 8, 2024 | Mar 20, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 8, 2024 | Mar 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 8, 2024 | Feb 27, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 8, 2024 | Feb 9, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Feb 8, 2024 | Feb 12, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2024 | Feb 9, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 12, 2024 | Mar 12, 2024 | Approved |
Mechanical plan review quality control Building Inspection · MECH-QC | Mar 19, 2024 | Mar 19, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 17, 2024 | May 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 1, 2024 | Jul 17, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2024 | Jul 3, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2024 | Jul 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2024 | Jul 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 1, 2024 | Jul 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 1, 2024 | Jul 2, 2024 | Approved |
Public health review Public Health · HEALTH | Jul 1, 2024 | Jul 1, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2024 | Jul 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 23, 2024 | Jul 25, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 24, 2024 | Jul 24, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 25, 2024 | Aug 8, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 25, 2024 | Jul 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2024 | Jul 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2024 | Jul 25, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 25, 2024 | Aug 5, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2024 | Jul 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 7, 2024 | Aug 7, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 12, 2024 | Aug 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2024 | Aug 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 12, 2024 | Aug 14, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 12, 2024 | Aug 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 12, 2024 | Sep 4, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 12, 2024 | Aug 19, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 12, 2024 | Aug 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2024 | Aug 14, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2024 | Aug 26, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 23, 2024 | Aug 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2024 | Sep 3, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 12, 2024 | Sep 12, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2024 | Sep 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2024 | Oct 31, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $447,197
| Name | Role | License on permit |
|---|---|---|
| Bo Zhang Beamable Engineering Inc | Engineer | C82956 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023