Remodel (e) 2-unit building including a horizontal addition at the rear, conversion of the (e) unconditioned basement to habitable space, expansion of a portion of the 1st floor to accommodate a new entry for the lower unit, and upgrade of all building systems.

Timeline
Key dates from the city record.
Filed
Oct 23, 2023
Issued
Aug 15, 2025 (22 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
19 stops across 5 departments
Comments issued
6 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 2, 2023Administrative

Zoning review

Planning · CP-ZOC

Apr 28, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jul 28, 2025Administrative

Building plan review

Building Inspection · BLDG

Sep 12, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 12, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 6, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Oct 29, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 9, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Oct 2, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Nov 12, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 29, 2024Approved

Building plan review

Building Inspection · BLDG

Dec 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 17, 2024Approved

Fire prevention review

Fire Department · SFFD

Dec 19, 2024Approved

Urban forestry

Public Works · DPW-BUF

Feb 27, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 27, 2025Approved

Street use and mapping

Public Works · DPW-BSM

May 28, 2025Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Jun 4, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 15, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Suspend
Estimated cost
$1,013,636
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Anne Noelle Fougeron

Fougeron Architecture

Architect18901
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202310239219 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record