1006 Bush St
San Francisco permit 202310239260 · Nob Hill
Owner improvement: intall walk-thru connecting adjacent commercial space. ada upgrades. new recessed entry, handrails, auto door opener.
- Filed
- Oct 23, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 14 stops across 6 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Oct 23, 2023 | Oct 23, 2023 | — |
Intake Building Inspection · INTAKE | Oct 23, 2023 | Oct 23, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 23, 2023 | Oct 23, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 23, 2023 | Oct 23, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 22, 2023 | Nov 22, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 22, 2023 | Nov 22, 2023 | Approved |
Intake Building Inspection · INTAKE | Dec 20, 2023 | Dec 20, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2023 | Dec 20, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2023 | Dec 20, 2023 | Approved |
Intake Building Inspection · INTAKE | Jan 24, 2024 | Jan 24, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 25, 2024 | Jan 25, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 25, 2024 | Jan 25, 2024 | Administrative |
Public health review Public Health · HEALTH | Jan 26, 2024 | Jan 26, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $35,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey J Burris Studio 12 Architecture | Architect | C27594 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026