460 Eddy St #0
San Francisco permit 202310239280 · Tenderloin
Relocation of existing paint booth and addition of a new paint booth & heater.
- Filed
- Oct 23, 2023
- Issued
- Dec 16, 2024 (14 months after filing)
- Completed
- Aug 28, 2025 (8 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 21 stops across 4 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 23, 2023 | Nov 9, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 9, 2023 | Jun 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 9, 2023 | Nov 25, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 4, 2024 | Jul 16, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 4, 2024 | Jul 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2024 | Jul 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 4, 2024 | Jul 17, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Jun 4, 2024 | Jun 6, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 10, 2024 | Jul 16, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 26, 2024 | Aug 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 7, 2024 | Oct 7, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 7, 2024 | Oct 7, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 9, 2024 | Oct 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 15, 2024 | Oct 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 16, 2024 | Oct 16, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 22, 2024 | Oct 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2024 | Nov 13, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 23, 2024 | Oct 24, 2024 | Approved |
Public health review Public Health · HEALTH | Oct 23, 2024 | Oct 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 13, 2024 | Nov 14, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 25, 2024 | Dec 16, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| James Gordon Fox Fox Engineering | Engineer | C21543 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025