1580 Beach St
San Francisco permit 202310249306 · Marina
Provide (6) adu's within existing envelope at first floor parking and storage per ord 162-16.
- Filed
- Oct 24, 2023
- Issued
- Sep 24, 2024 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 23 stops across 5 departments
- Comments issued
- 5 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2023 | Oct 24, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 24, 2023 | Apr 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Dec 15, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2023 | Dec 15, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 24, 2023 | Nov 7, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2023 | Oct 25, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 24, 2023 | Nov 8, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 24, 2023 | Sep 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 1, 2024 | Feb 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2024 | Feb 7, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 1, 2024 | Feb 14, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2024 | Feb 6, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 1, 2024 | May 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2024 | Feb 7, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 11, 2024 | Mar 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2024 | Mar 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2024 | Mar 27, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2024 | Mar 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2024 | Mar 14, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 12, 2024 | Mar 12, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 30, 2024 | Aug 30, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Sep 3, 2024 | Sep 3, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 3, 2024 | Sep 24, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Joseph Paris Thousand Architects | Architect | C30755 |
| Ali Afrasiabi Rei Build Up Design | Engineer | S-5413 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025