San Francisco permit 202310249306 · Marina

ADUFull plan reviewIssued
Street view · Jan 2025
Google Street View of 1580 Beach St, Jan 2025
Scope of work
As written on the permit application.

Provide (6) adu's within existing envelope at first floor parking and storage per ord 162-16.

Timeline
Key dates from the city record.
Filed
Oct 24, 2023
Issued
Sep 24, 2024 (11 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 5 departments
Comments issued
5 times, by Planning, Building Inspection, Fire Department
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 24, 2023Administrative

Zoning review

Planning · CP-ZOC

Apr 15, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Dec 15, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 15, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 7, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 25, 2023Approved

Urban forestry

Public Works · DPW-BUF

Nov 8, 2023Approved

Permit Processing Center

Building Inspection · PPC

Sep 3, 2024Administrative

Building plan review

Building Inspection · BLDG

Feb 26, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 7, 2024Approved

Fire prevention review

Fire Department · SFFD

Feb 14, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 6, 2024Approved

Urban forestry

Public Works · DPW-BUF

May 23, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 7, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 12, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 27, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 20, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 14, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 12, 2024Approved

Zoning review

Planning · CP-ZOC

Aug 30, 2024Approved

Development fee collection

Building Inspection · DFCU

Sep 3, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Sep 24, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$250,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Daniel Joseph Paris

Thousand Architects

ArchitectC30755
Ali Afrasiabi

Rei Build Up Design

EngineerS-5413
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202310249306 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record