1042 Pacheco St
San Francisco permit 202310249322 · Inner Sunset
New 1st & 2nd floor decks at rear of existing single family dwelling; interior alterations at 1st floor, adding bathroom & bedroom - no new dwelling unit.
- Filed
- Oct 24, 2023
- Issued
- May 16, 2024 (7 months after filing)
- Completed
- Apr 15, 2025 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 45 stops across 6 departments
- Comments issued
- 14 times, by Building Inspection, Public Utilities, Public Works, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2023 | Nov 16, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 16, 2023 | Feb 29, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 16, 2023 | May 15, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jan 9, 2024 | Jan 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 29, 2024 | Mar 11, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 29, 2024 | Apr 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 29, 2024 | Mar 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 29, 2024 | Mar 7, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2024 | Apr 15, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 18, 2024 | Apr 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2024 | Apr 22, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 26, 2024 | Apr 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 29, 2024 | Apr 30, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | May 8, 2024 | May 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 9, 2024 | May 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 9, 2024 | May 10, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 9, 2024 | May 14, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2024 | May 14, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 9, 2024 | May 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 15, 2024 | May 16, 2024 | Administrative |
Addendum 1: Struct,arch,t-24,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 23, 2024 | Jun 4, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 29, 2024 | May 29, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 3, 2024 | Jun 3, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 4, 2024 | Jun 4, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jun 5, 2024 | Jun 14, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 10, 2024 | Jun 10, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 12, 2024 | Jun 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2024 | Jun 17, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 17, 2024 | Jul 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 17, 2024 | Jul 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 17, 2024 | Jun 25, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 17, 2024 | Jun 24, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 17, 2024 | Sep 24, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2024 | Jun 28, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 23, 2024 | Jul 23, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2024 | Jul 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 27, 2024 | Aug 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 6, 2024 | Sep 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2024 | Sep 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 10, 2024 | Sep 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 10, 2024 | Sep 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 10, 2024 | Sep 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2024 | Sep 24, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 24, 2024 | Sep 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 24, 2024 | Sep 24, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $77,785
| Name | Role | License on permit |
|---|---|---|
| Stephen Antonaros Stephen Antonaros Architect | Architect | C14386 |
| Victor Ramos Ashley & Vance Engineering | Engineer | C86568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022