523 Broadway
San Francisco permit 202310249342 · North Beach
Ti of exist. restaurant. new equipment under (e) hood, new bar service. adding night time entertianment.
- Filed
- Oct 24, 2023
- Issued
- Oct 16, 2024 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 16 times, by Planning, Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 24, 2023 | Oct 24, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 24, 2023 | Oct 24, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 8, 2023 | Nov 8, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 8, 2023 | Nov 8, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 5, 2023 | Dec 5, 2023 | Issued Comments |
Apartment and hotel inspection Building Inspection · HIS | Jan 19, 2024 | Jan 19, 2024 | Administrative |
Intake Building Inspection · INTAKE | Jan 19, 2024 | Jan 19, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 24, 2024 | Jan 24, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 25, 2024 | Jan 25, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 31, 2024 | Jan 31, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 31, 2024 | Jan 31, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 9, 2024 | Feb 9, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 9, 2024 | Feb 9, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | May 23, 2024 | May 23, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 23, 2024 | May 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 23, 2024 | May 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 23, 2024 | May 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2024 | May 23, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | May 23, 2024 | May 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 23, 2024 | May 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 26, 2024 | Jun 26, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 26, 2024 | Jun 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 26, 2024 | Jun 26, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Jul 11, 2024 | Jul 11, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 11, 2024 | Jul 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Jul 11, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Aug 6, 2024 | Aug 6, 2024 | Administrative |
Public health food review Public Health · HEALTH-FD | Aug 6, 2024 | Aug 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 30, 2024 | Sep 30, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 30, 2024 | Sep 30, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 30, 2024 | Sep 30, 2024 | Approved |
Public health food review Public Health · HEALTH-FD | Sep 30, 2024 | Sep 30, 2024 | Administrative |
Intake Building Inspection · INTAKE | Oct 8, 2024 | Oct 8, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Oct 8, 2024 | Oct 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 8, 2024 | Oct 8, 2024 | Approved |
Public health food review Public Health · HEALTH-FD | Oct 8, 2024 | Oct 16, 2024 | Administrative |
Public health food review Public Health · HEALTH-FD | Oct 16, 2024 | Oct 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 16, 2024 | Oct 16, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| David Joe Elliott David J. Elliott & Associates | Architect | C11776 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025