As written on the permit application.

Priority processing: new 6-story type iiia over type 1a mixed-use bldg with 35 studio units (100% affordable housing mayor ed 13-01), residential community space, and commercial/retail space on 1st floor. preserve (e) 2-story facade along mission st and 29th st.

Timeline
Key dates from the city record.
Filed
Oct 25, 2023
Issued
Jul 5, 2024 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
149 stops across 6 departments
Comments issued
40 times, by Building Inspection, Fire Department, Public Utilities, Public Works, Permit Center, Planning

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 17, 2023Administrative

Apartment and hotel inspection

Building Inspection · HIS

Nov 17, 2023Approved

Code enforcement

Building Inspection · CES

Nov 17, 2023—

Zoning review

Planning · CP-ZOC

Feb 12, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jul 3, 2024Administrative

Building plan review

Building Inspection · BLDG

Feb 20, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 22, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 21, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 14, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 8, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 13, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 25, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 27, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 3, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Apr 8, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Mar 22, 2024Approved

Zoning review

Planning · CP-ZOC

Mar 21, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 3, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 3, 2024Approved

Zoning review

Planning · CP-ZOC

Apr 24, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 8, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 9, 2024Approved-Stipulated

Development fee collection

Building Inspection · DFCU

Apr 23, 2024Administrative

Building plan review

Building Inspection · BLDG

Apr 24, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 25, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 24, 2024Approved

Street use and mapping

Public Works · DPW-BSM

May 1, 2024Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

May 7, 2024Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Jul 5, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

Jun 20, 2024Approved-Stipulated

Addendum 1: Foundation + superstructure

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 22, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Jul 16, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jul 19, 2024Not Applicable

Electrical pre-screening

Building Inspection · PRE-MECH-E

Jul 19, 2024Not Applicable

Central Permit Bureau

Building Inspection · CPB

Jul 22, 2024Administrative

Building plan review

Building Inspection · BLDG

Oct 7, 2024Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Oct 15, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

Jul 23, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Mar 14, 2025Administrative

Urban forestry

Public Works · DPW-BUF

Sep 19, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Nov 14, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Dec 5, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 3, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 4, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Mar 4, 2025Administrative

Street use and mapping

Public Works · DPW-BSM

Mar 5, 2025Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Mar 4, 2025Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Mar 20, 2025Administrative

Addendum 2: Arch, mep

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 22, 2024Issued Comments

Central Permit Bureau

Building Inspection · CPB

Jan 13, 2025Administrative

Building pre-screening

Building Inspection · PRE-BLDG

Jul 19, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jul 19, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Jul 19, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Dec 12, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Dec 5, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Dec 10, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Dec 12, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jan 13, 2025Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jan 13, 2025Approved

Zoning review

Planning · CP-ZOC

Feb 24, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jan 28, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 28, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 23, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 16, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 13, 2025Approved

Permit Processing Center

Building Inspection · PPC

Aug 7, 2025Administrative

Urban forestry

Public Works · DPW-BUF

Mar 4, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Apr 25, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 25, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 31, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 31, 2025Not Applicable

Building plan review

Building Inspection · BLDG

Mar 31, 2025Not Applicable

Fire prevention review

Fire Department · SFFD

Apr 25, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Apr 22, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Apr 24, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 24, 2025Approved

Building plan review

Building Inspection · BLDG

May 21, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

May 9, 2025Approved

Fire prevention review

Fire Department · SFFD

May 13, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 13, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 9, 2025Approved

Zoning review

Planning · CP-ZOC

May 15, 2025Approved

Electrical plan review

Building Inspection · MECH-E

May 20, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 30, 2025Approved

Zoning review

Planning · CP-ZOC

Jun 18, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 23, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 5, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 23, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Jun 7, 2025Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Jun 10, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jul 9, 2025Approved

Urban forestry

Public Works · DPW-BUF

Jun 30, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 8, 2025Administrative

Addendum 3: Superstructure (structural)

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Apr 10, 2025Administrative

Building plan review

Building Inspection · BLDG

May 16, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 16, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Apr 24, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jul 11, 2025Administrative

Urban forestry

Public Works · DPW-BUF

Jun 26, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 13, 2025Approved-Stipulated

Building plan review

Building Inspection · BLDG

Jun 13, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jul 3, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 17, 2025Administrative

Addendum 4: Fire sprinklers

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 9, 2025Administrative

Building plan review

Building Inspection · BLDG

Oct 23, 2025Not Applicable

Fire Department housing review

Fire Department · SFFD-HQ

Oct 28, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Dec 17, 2025Administrative

Fire Department housing review

Fire Department · SFFD-HQ

Dec 9, 2025Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Dec 16, 2025Approved

Fire Department housing review

Fire Department · SFFD-HQ

Dec 17, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 19, 2025Administrative

Addendum 5: Metal stairs

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 9, 2025Administrative

Building plan review

Building Inspection · BLDG

Oct 27, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 24, 2025Not Applicable

Fire Department housing review

Fire Department · SFFD-HQ

Oct 28, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Mar 17, 2026Administrative

Building plan review

Building Inspection · BLDG

Jan 22, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Jan 23, 2026Approved-Stipulated

Building plan review

Building Inspection · BLDG

Mar 10, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Mar 12, 2026Approved-Stipulated

Building plan review

Building Inspection · BLDG

Mar 16, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Mar 17, 2026Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Mar 19, 2026Administrative

Addendum 6: Fire alarm & 2 way communication

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 15, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 17, 2025Administrative

Building plan review

Building Inspection · BLDG

Oct 23, 2025Not Applicable

Fire Department housing review

Fire Department · SFFD-HQ

Nov 7, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Mar 18, 2026Administrative

Fire Department housing review

Fire Department · SFFD-HQ

Feb 17, 2026Approved-Stipulated

Fire Department housing review

Fire Department · SFFD-HQ

Mar 18, 2026Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Mar 19, 2026Administrative

Addendum 7: Exterior bldg maintenance(ebm)

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 14, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jan 15, 2026Administrative

Building plan review

Building Inspection · BLDG

Feb 24, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 2, 2026Not Applicable

Fire Department housing review

Fire Department · SFFD-HQ

Jan 26, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Jan 28, 2026Approved

Permit Processing Center

Building Inspection · PPC

Apr 3, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 6, 2026Administrative

Addendum 8: Revise approved site permit proj description to specify (e) bldg will be demolished in its entirety

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

In progress—

Addendum 9: Revision to issued s-4, fire sprinklers.

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 15, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 15, 2026Administrative

Fire Department housing review

Fire Department · SFFD-HQ

Apr 16, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

May 5, 2026Administrative

Fire Department housing review

Fire Department · SFFD-HQ

May 5, 2026Approved

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Reinstated
Estimated cost
$17,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Christian Niel Haegglund

Bar Architects

ArchitectC-18896
Ben Au

Holmes

EngineerS4938
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202310259516 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record