1730 Ofarrell St
San Francisco permit 202310269522 · Western Addition
Voluntary partial structural strengthening - reinforced concrete column jackets/wall overlays at street shearwalls. removal & replacement of architectural finishes to allow for structural work to be completed, ada upgrades of residential lobby.
- Filed
- Oct 26, 2023
- Issued
- Mar 8, 2024 (4 months after filing)
- Completed
- Apr 16, 2025 (13 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- Once, by Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Oct 26, 2023 | Oct 26, 2023 | Administrative |
Plumbing inspector Building Inspection · PID-INSP | Oct 26, 2023 | Oct 26, 2023 | Approved |
Intake Building Inspection · INTAKE | Oct 26, 2023 | Oct 26, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 30, 2023 | Oct 30, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 30, 2023 | Oct 30, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2023 | Nov 3, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 6, 2023 | Nov 6, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2023 | Nov 6, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 6, 2023 | Nov 6, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 15, 2023 | Nov 16, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 16, 2023 | Jan 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2024 | Feb 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 16, 2024 | Feb 22, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 22, 2024 | Feb 26, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2024 | Mar 8, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Sandy Sxi-Ai Blair | Architect | C29691 |
| Alexander Michael Santos Altos Engineering | Engineer | C84144 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026