1977 Bush St
San Francisco permit 202310309767 · Pacific Heights
Remove (e) rear stairs, walls and windows. replace in kind. repair dry rot. no work to front facade
- Filed
- Oct 30, 2023
- Issued
- Apr 12, 2024 (5 months after filing)
- Completed
- May 14, 2025 (13 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 6 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 30, 2023 | Oct 30, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 30, 2023 | Oct 30, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 13, 2023 | Nov 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2023 | Nov 13, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2023 | Nov 13, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2024 | Apr 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $25,000
| Name | Role | License on permit |
|---|---|---|
| Darrel Wayne Harris | Engineer | 2433 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022