As written on the permit application.

Front: new single family home to be built over existing two car garage.

Timeline
Key dates from the city record.
Filed
Oct 31, 2023
Issued
Jul 25, 2025 (21 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
49 stops across 5 departments
Comments issued
21 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 27, 2023Administrative

Zoning review

Planning · CP-ZOC

Apr 15, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Jul 14, 2025Administrative

Zoning review

Planning · CP-ZOC

Aug 30, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 11, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Oct 18, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 25, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 20, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 12, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Nov 4, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 16, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 25, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Oct 21, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jan 7, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 15, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 9, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 24, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 3, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 15, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Feb 28, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 13, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 24, 2025Issued Comments

Zoning review

Planning · CP-ZOC

May 23, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 7, 2025Administrative

Structural plan approval

Building Inspection · PAD-STR

Apr 1, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 21, 2025Approved

Fire prevention review

Fire Department · SFFD

Mar 26, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 27, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Apr 27, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Mar 31, 2025Approved

Fire prevention review

Fire Department · SFFD

Apr 8, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 9, 2025Administrative

Street use and mapping

Public Works · DPW-BSM

May 12, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

May 15, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jun 4, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

May 30, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jun 18, 2025Approved

Fire prevention review

Fire Department · SFFD

May 22, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

May 28, 2025Approved

Urban forestry

Public Works · DPW-BUF

Jun 27, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

May 27, 2025Approved

Zoning review

Planning · CP-ZOC

Jun 5, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 6, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 6, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 10, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jun 11, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 9, 2025Approved

Development fee collection

Building Inspection · DFCU

Jul 2, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Jul 25, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,342,572
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Patrick B Perez

Design Pad

Architect30230
Preston Nirattisai

Prostruct Engineering

EngineerC85115
Nicholas Kennedy

Anura Design

EngineerS6884
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202310319891 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record