2930 Laguna St
San Francisco permit 202310319892 · Marina
Main rear: 1/f: renovate (e) bathroom, add shower, create new cooridor alongside garage for exit access to rear living space, new sliding glass door at rear living space and new exterior steps to deck. 2/f: no work. 3/f: 100sf addition to rear bedroom, renovate and expand existing. demo chimney.
- Filed
- Oct 31, 2023
- Issued
- Jul 25, 2025 (21 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 35 stops across 5 departments
- Comments issued
- 13 times, by Planning, Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 31, 2023 | Nov 27, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 27, 2023 | Apr 17, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 27, 2023 | Jul 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2024 | Jun 12, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 9, 2024 | Aug 30, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 30, 2024 | Aug 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 3, 2024 | Oct 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 3, 2024 | Sep 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 3, 2024 | Sep 12, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 3, 2024 | Sep 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 18, 2024 | Apr 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 3, 2025 | Jan 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 3, 2025 | Jan 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 3, 2025 | Jan 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 3, 2025 | Jan 24, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 3, 2025 | Jan 15, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 3, 2025 | Jan 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2025 | Feb 24, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 25, 2025 | May 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 25, 2025 | Apr 7, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 25, 2025 | Apr 1, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2025 | Apr 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2025 | Apr 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2025 | Mar 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 20, 2025 | Jun 6, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 20, 2025 | Jun 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2025 | Jun 18, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 20, 2025 | Jun 2, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 20, 2025 | Jun 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 20, 2025 | May 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 5, 2025 | Jun 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2025 | Jun 10, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2025 | Jun 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2025 | Jun 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2025 | Jul 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $158,293
| Name | Role | License on permit |
|---|---|---|
| Patrick B Perez Design Pad | Architect | 30230 |
| Preston Nirattisai Prostruct Engineering | Engineer | C85115 |
| Nicholas Kennedy Anura Design | Engineer | S6884 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026