763 Kansas St
San Francisco permit 202311030086 · Potrero Hill
3 story horizontal rear addition to n.east and s.east corners of front bldg, incl interior remodel at all floors for (n) media rm & office at 1st fl, (n) kitchen & pwdr rm @ 2nd fl, 2(n) baths, 1(n) bdrm, & (n) lndry rm @ 3rd fl. (n) roof deck at lvl 4. no work at (e) r-3 cottage @ rear of lot.
- Filed
- Nov 3, 2023
- Issued
- Feb 4, 2025 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 41 stops across 6 departments
- Comments issued
- 12 times, by Planning, Building Inspection, Public Utilities, Fire Department, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 3, 2023 | Nov 27, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 27, 2023 | Feb 7, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 27, 2023 | Jan 29, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 2, 2024 | Jul 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Jul 26, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2024 | Jul 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2024 | Jul 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 30, 2024 | Nov 6, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 30, 2024 | Nov 11, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 30, 2024 | Dec 11, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Dec 4, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 9, 2025 | Jan 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2025 | Jan 9, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2025 | Jan 9, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2025 | Jan 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 15, 2025 | Jan 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 16, 2025 | Jan 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2025 | Jan 16, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 16, 2025 | Jan 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 16, 2025 | Jan 23, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 16, 2025 | Jan 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 17, 2025 | Jan 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 29, 2025 | Feb 4, 2025 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2025 | Feb 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2025 | Feb 27, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 28, 2025 | Apr 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 28, 2025 | Apr 6, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 28, 2025 | Mar 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 28, 2025 | Mar 4, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 28, 2025 | Mar 4, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 28, 2025 | Feb 28, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 28, 2025 | May 5, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2025 | Mar 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2025 | Apr 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | Apr 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | Apr 23, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 1, 2025 | May 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 1, 2025 | May 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 1, 2025 | May 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2025 | May 1, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 5, 2025 | May 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $575,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Johnston Rodgers Rodgers Architecture | Architect | C30697 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026