339 Faxon Av
San Francisco permit 202311030091 · Oceanview/Merced/Ingleside
Convert 1st story basement to finished space. full 2nd story remodel.structural strengthening.addition of 250sqft to back of hosue w/deck above for master bedroom
- Filed
- Nov 3, 2023
- Issued
- May 9, 2025 (18 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 36 stops across 4 departments
- Comments issued
- 19 times, by Planning, Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 3, 2023 | Jan 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 31, 2024 | Apr 18, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 31, 2024 | Mar 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 30, 2024 | Jun 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 14, 2024 | Jul 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 14, 2024 | Jul 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 14, 2024 | Jun 27, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 14, 2024 | Jul 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 26, 2024 | Jul 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 28, 2024 | Sep 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2024 | Sep 11, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2024 | Sep 5, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 28, 2024 | Aug 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2024 | Sep 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 9, 2024 | Sep 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2024 | Oct 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2024 | Dec 3, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2024 | Oct 31, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2024 | Oct 30, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 28, 2024 | Oct 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2024 | Nov 1, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 30, 2024 | Nov 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 5, 2024 | Nov 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2024 | Nov 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2024 | Nov 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2024 | Dec 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 9, 2024 | Dec 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 7, 2025 | Jan 23, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 7, 2025 | Mar 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 7, 2025 | Jan 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 7, 2025 | Jan 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2025 | Jan 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2025 | Jan 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 27, 2025 | Jan 29, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 6, 2025 | Mar 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2025 | May 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $446,000
| Name | Role | License on permit |
|---|---|---|
| Luis Rodriguez | Architect | 87060 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022