1983 34th Av
San Francisco permit 202311030096 · Sunset/Parkside
Remove (e) ground fl single story rear addition & build (n) ground floor single story addition setback from side property lines. legalize wall & door at ground fl garage. legalize ground fl as-built condition including bathroom that differs from completed pa# 8806345 r1. ref complaint # 202310496.
- Filed
- Nov 3, 2023
- Issued
- Sep 11, 2024 (10 months after filing)
- Completed
- Jan 23, 2025 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 17 stops across 3 departments
- Comments issued
- 5 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 3, 2023 | Nov 10, 2023 | Administrative |
Building inspector Building Inspection · BID-INSP | Nov 8, 2023 | Nov 8, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 10, 2023 | Feb 1, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 10, 2023 | Jul 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 27, 2024 | Apr 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 1, 2024 | Jun 3, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 1, 2024 | May 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2024 | Apr 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 1, 2024 | Apr 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 27, 2024 | Jun 27, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 28, 2024 | Jun 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 12, 2024 | Jul 12, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 17, 2024 | Jul 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 18, 2024 | Jul 18, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 18, 2024 | Jul 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 18, 2024 | Jul 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 26, 2024 | Sep 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $61,352
| Name | Role | License on permit |
|---|---|---|
| P Vincent Gonzaga Vincent Gonzaga Architect | Architect | C33614 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2019