9 Tioga Av
San Francisco permit 202311030120 · Visitacion Valley
Enclose existing front porch, 3bedrom, 2bath. convert grd floor back of garage to master bedroom. kitchen and bathroom remodel, window replacement, painting, flooring, plumbing, electrical replacement. infill lightwell.
- Filed
- Nov 3, 2023
- Issued
- Jul 31, 2025 (21 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 8 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 3, 2023 | Nov 3, 2023 | Administrative |
Intake Building Inspection · INTAKE | Dec 28, 2023 | Dec 28, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 28, 2023 | Dec 28, 2023 | Issued Comments |
Intake Building Inspection · INTAKE | Jan 18, 2024 | Jan 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 18, 2024 | Jan 18, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 20, 2024 | Feb 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 25, 2024 | Apr 25, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 8, 2024 | May 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2024 | May 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 28, 2024 | May 28, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2024 | May 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2024 | May 28, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 28, 2024 | May 28, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 5, 2024 | Jul 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 6, 2024 | Aug 6, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 21, 2024 | Aug 21, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 31, 2025 | Jul 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2025 | Jul 31, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 31, 2025 | Jul 31, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Narasimha D Prasanth Tanikella | Engineer | S6568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022