66 Mirabel Av
San Francisco permit 202311060197 · Bernal Heights
Remodel 2 units including replacement of mechanical, plumbing & electrical system. replacement of all windows & installation of insulation throughout. ground floor addition of 404 ft of heated space within garage envelope. infill (e) lightwell. replace stucco facade with new painted wood siding.
- Filed
- Nov 6, 2023
- Issued
- Apr 17, 2024 (5 months after filing)
- Completed
- Sep 18, 2025 (17 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- 5 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 6, 2023 | Nov 6, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 6, 2023 | Nov 6, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 6, 2023 | Nov 6, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 8, 2023 | Nov 8, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Nov 9, 2023 | Nov 10, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 10, 2023 | Jan 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 10, 2024 | Feb 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 1, 2024 | Feb 7, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2024 | Feb 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2024 | Feb 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2024 | Mar 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2024 | Feb 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 5, 2024 | Mar 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2024 | Mar 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2024 | Mar 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 18, 2024 | Mar 20, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 21, 2024 | Mar 21, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2024 | Apr 17, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $864,852
| Name | Role | License on permit |
|---|---|---|
| Mike Patrick Larkin Mike Larkin Architecture | Architect | C25214 |
| Vladimir Rabichev Optimal Design Group | Engineer | C35314 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023