66 Mirabel Av

San Francisco permit 202311060197 · Bernal Heights

AdditionFull plan reviewComplete
Street view · Jan 2023
Google Street View of 66 Mirabel Av, Jan 2023
Scope of work
As written on the permit application.

Remodel 2 units including replacement of mechanical, plumbing & electrical system. replacement of all windows & installation of insulation throughout. ground floor addition of 404 ft of heated space within garage envelope. infill (e) lightwell. replace stucco facade with new painted wood siding.

Timeline
Key dates from the city record.
Filed
Nov 6, 2023
Issued
Apr 17, 2024 (5 months after filing)
Completed
Sep 18, 2025 (17 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
18 stops across 5 departments
Comments issued
5 times, by Planning, Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Nov 6, 2023Administrative

Zoning review

Planning · CP-ZOC

Nov 6, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Nov 6, 2023Approved

Permit Center

Permit Center · PERMIT-CTR

Nov 8, 2023—

Central Permit Bureau

Building Inspection · CPB

Nov 10, 2023Administrative

Building plan review

Building Inspection · BLDG

Jan 9, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 8, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 7, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 12, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Feb 16, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 1, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 21, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 5, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 11, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 18, 2024Approved

Zoning review

Planning · CP-ZOC

Mar 20, 2024Approved

Permit Processing Center

Building Inspection · PPC

Mar 21, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 17, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$864,852
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mike Patrick Larkin

Mike Larkin Architecture

ArchitectC25214
Vladimir Rabichev

Optimal Design Group

EngineerC35314
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202311060197 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record