915 Haight St
San Francisco permit 202311060280 · Haight Ashbury
Remove portion of (e) roof and rpelace with new shed roofs to increase headroom. install new deck at rear of 4/f level. convert attice space to habitable space connected to (e) third floor.
- Filed
- Nov 6, 2023
- Issued
- Jul 15, 2025 (20 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 39 stops across 6 departments
- Comments issued
- 12 times, by Building Inspection, Public Works, Fire Department, Public Utilities
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 14, 2023 | Dec 20, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 20, 2023 | Apr 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 22, 2023 | Jan 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 14, 2025 | Feb 7, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 14, 2025 | Jan 24, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 14, 2025 | Jan 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 14, 2025 | Jan 23, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2025 | Feb 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 3, 2025 | Mar 13, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2025 | Mar 20, 2025 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Mar 3, 2025 | Mar 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2025 | Mar 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 14, 2025 | Apr 18, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 14, 2025 | Apr 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 14, 2025 | Apr 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2025 | Apr 24, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2025 | Apr 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2025 | Jul 15, 2025 | Administrative |
Addendum 1: Final - architectural, t-24, mep,superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 16, 2025 | Jul 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2025 | Jul 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 25, 2025 | Jul 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 25, 2025 | Sep 4, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 25, 2025 | Sep 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2025 | Aug 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 25, 2025 | Oct 9, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2025 | Jul 31, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2025 | Aug 5, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 25, 2025 | Dec 4, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 8, 2025 | Oct 8, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Oct 8, 2025 | Oct 8, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 28, 2025 | Oct 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2025 | Nov 3, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 18, 2025 | Nov 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 19, 2025 | Nov 21, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 19, 2025 | Dec 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 19, 2025 | Nov 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 19, 2025 | Nov 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 19, 2025 | Dec 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 4, 2025 | May 1, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $245,435
| Name | Role | License on permit |
|---|---|---|
| Rex Stuart Mclean Rex Mclean Architect | Architect | C-14477 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022