88 Chilton Av
San Francisco permit 202311070303 · Glen Park
Remodel existing 1st flr. family room w/wet bar to include 2nd kitchen per planning code section 102. 2nd kitchen to have 2 burner cooktop, sink, dishwasher, fridge and microwave. new lighting, new cabinets and new flooring. no changes to exterior.
- Filed
- Nov 7, 2023
- Issued
- Nov 7, 2023 (within 1 month of filing)
- Completed
- Mar 20, 2024 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 6 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 7, 2023 | Nov 7, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 7, 2023 | Nov 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2023 | Nov 7, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2023 | Nov 7, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2023 | Nov 7, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2023 | Nov 7, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $35,000
| Name | Role | License on permit |
|---|---|---|
| Liza A Pannozzo Lapnog Arch. | Architect | C26905 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015