1944 Great Hy
San Francisco permit 202311080469 · Sunset/Parkside
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to 202308114295 to include roof deck & roof latch with interior stairs and move skylight over dinning.
- Filed
- Nov 8, 2023
- Issued
- Nov 17, 2023 (within 1 month of filing)
- Completed
- Feb 6, 2025 (15 months after issuance)
- Review stops
- 7 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 8, 2023 | Nov 8, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 8, 2023 | Nov 8, 2023 | Approved |
Intake Building Inspection · INTAKE | Nov 16, 2023 | Nov 16, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 16, 2023 | Nov 16, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 16, 2023 | Nov 16, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 16, 2023 | Nov 16, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 17, 2023 | Nov 17, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $10,000
| Name | Role | License on permit |
|---|---|---|
| Sandra L Chan | Architect | C27326 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022