232 Holladay Av
San Francisco permit 202311090527 · Bernal Heights
To resolve nov 202313515. restore hillside to previous existing condition.
- Filed
- May 9, 2024
- Issued
- May 23, 2025 (12 months after filing)
- Completed
- Jul 16, 2025 (2 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 35 stops across 4 departments
- Comments issued
- 7 times, by Building Inspection, Permit Center
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 9, 2023 | Nov 9, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 9, 2023 | Nov 9, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 9, 2023 | Nov 9, 2023 | — |
Building inspector Building Inspection · BID-INSP | Nov 9, 2023 | Mar 18, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 13, 2023 | Nov 13, 2023 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 13, 2023 | Nov 13, 2023 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 14, 2024 | Mar 21, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Mar 15, 2024 | May 9, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 18, 2024 | Mar 18, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 18, 2024 | Mar 18, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Apr 25, 2024 | May 8, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 29, 2024 | Apr 29, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | May 1, 2024 | May 1, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | May 2, 2024 | May 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 9, 2024 | May 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 9, 2024 | Jun 28, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 9, 2024 | May 24, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 9, 2024 | May 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 30, 2024 | Jul 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 30, 2024 | Aug 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 30, 2024 | Jul 31, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 29, 2024 | Oct 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 29, 2024 | Nov 14, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2024 | Oct 30, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 12, 2025 | Feb 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Feb 19, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2025 | Feb 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 25, 2025 | Feb 25, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 7, 2025 | Apr 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 7, 2025 | Apr 16, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2025 | Apr 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 29, 2025 | Apr 30, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 30, 2025 | May 1, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 30, 2025 | May 1, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 1, 2025 | May 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $14,000
| Name | Role | License on permit |
|---|---|---|
| Lauren Marie Wingert Lauren Wingert | Engineer | C80032 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022