359 Waller St #5
San Francisco permit 202311090562 · Hayes Valley
#5: creating 2nd bathroom w/water closet, shower, and lavatory. replace glass sliding door in kind. new skylight. no deck work.
- Filed
- Nov 9, 2023
- Issued
- Dec 5, 2023 (within 1 month of filing)
- Completed
- May 9, 2024 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Twice, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Nov 9, 2023 | Nov 9, 2023 | — |
Intake Building Inspection · INTAKE | Nov 9, 2023 | Nov 9, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 9, 2023 | Nov 9, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 16, 2023 | Nov 16, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 28, 2023 | Nov 28, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 5, 2023 | Dec 5, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 5, 2023 | Dec 5, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2023 | Dec 5, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 5, 2023 | Dec 5, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2023 | Dec 5, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 5, 2023 | Dec 5, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $43,000
| Name | Role | License on permit |
|---|---|---|
| Anthony Castro Roxas Arxarch | Architect | C-37259 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022