2025 Van Ness Av

San Francisco permit 202311130657 · Pacific Heights

Commercial or tenant improvementFull plan reviewComplete
Street view · Apr 2019
Google Street View of 2025 Van Ness Av, Apr 2019
Scope of work
As written on the permit application.

Tenant improvement of an existing commerical retail space, including: 1. exterior storefront and finishes 2. structural framing/bracing 3. interior non-bearing partitions 4. millwork and interior finishes 5. mep 6. civil - ada path of travel and parking compliance

Timeline
Key dates from the city record.
Filed
Nov 13, 2023
Issued
May 20, 2024 (6 months after filing)
Completed
Oct 7, 2025 (17 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
33 stops across 5 departments
Comments issued
11 times, by Building Inspection, Public Utilities, Public Works
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 1, 2023Administrative

Code enforcement

Building Inspection · CES

Nov 20, 2023—

Zoning review

Planning · CP-ZOC

Dec 22, 2023Approved

Permit Processing Center

Building Inspection · PPC

May 16, 2024Administrative

Building plan review

Building Inspection · BLDG

Mar 1, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 16, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 11, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 6, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

Jan 22, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 9, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 16, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Feb 21, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Apr 3, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 29, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 28, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Mar 21, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 26, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Apr 9, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 5, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 22, 2024Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Apr 2, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 4, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Apr 5, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Apr 16, 2024Approved

Zoning review

Planning · CP-ZOC

Apr 11, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 18, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 16, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Apr 11, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 23, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 15, 2024Approved

Street use and mapping

Public Works · DPW-BSM

May 13, 2024Approved

Fire prevention review

Fire Department · SFFD

May 15, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

May 20, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$3,400,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Shawn M Anderson

Msa Architecture

ArchitectC31273
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202311130657 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record