1371 Grant Av
San Francisco permit 202311130670 · North Beach
Renovation of (e) bar with new bar, accessible entry, accessible bathroom, new stairs, new partitions, new lighting and electrical, new equipment.
- Filed
- Nov 13, 2023
- Issued
- Dec 8, 2023 (within 1 month of filing)
- Completed
- Jun 18, 2024 (6 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 19 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Nov 13, 2023 | Nov 13, 2023 | Administrative |
Intake Building Inspection · INTAKE | Nov 13, 2023 | Nov 13, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 13, 2023 | Nov 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2023 | Nov 13, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 17, 2023 | Nov 17, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 17, 2023 | Nov 17, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 17, 2023 | Nov 17, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 17, 2023 | Nov 17, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2023 | Nov 21, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 21, 2023 | Nov 21, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2023 | Nov 21, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2023 | Nov 21, 2023 | Approved |
Public health review Public Health · HEALTH | Nov 21, 2023 | Nov 21, 2023 | Administrative |
Public health food review Public Health · HEALTH-FD | Nov 21, 2023 | Nov 29, 2023 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Nov 30, 2023 | Nov 30, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 4, 2023 | Dec 4, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 4, 2023 | Dec 4, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2023 | Dec 8, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 8, 2023 | Dec 8, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $246,460
| Name | Role | License on permit |
|---|---|---|
| Nicholas Wilkes Polansky | Architect | C-40671 |
| Reece Relatores Relatores Structural | Engineer | C84126 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026