999 Laguna St
San Francisco permit 202311140774 · Western Addition
At&t: install 3 new antennas, new antenna mounts, new frp screen extension. install 1 new cabinet, 8 new batteries.
- Filed
- Nov 14, 2023
- Issued
- Oct 8, 2024 (11 months after filing)
- Completed
- Jan 10, 2025 (3 months after issuance)
- Review stops
- 9 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Nov 14, 2023 | Nov 14, 2023 | Administrative |
Intake Building Inspection · INTAKE | Nov 14, 2023 | Nov 14, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 14, 2023 | Nov 14, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 14, 2023 | Nov 14, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2023 | Nov 14, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 14, 2023 | Nov 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 14, 2023 | Nov 14, 2023 | Approved |
Public health review Public Health · HEALTH | Nov 14, 2023 | Nov 15, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 8, 2024 | Oct 8, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $55,000
| Name | Role | License on permit |
|---|---|---|
| Chris Lee | Engineer | C61054 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025