100 Clipper St
San Francisco permit 202311150826 · Noe Valley
Change of use and occupancy from b-office to group e daycare. commercial ti for new day care facility. 25 students. no horizontal or vertical addition. revise (e) restrooms to be accessible.no structural work. age range 36mo-5yr.
- Filed
- Nov 15, 2023
- Issued
- Aug 1, 2024 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 36 stops across 7 departments
- Comments issued
- 7 times, by Public Works, Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 15, 2023 | Nov 15, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 16, 2023 | Nov 16, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2023 | Nov 21, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 6, 2024 | Feb 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 8, 2024 | Feb 8, 2024 | Approved |
Public health review Public Health · HEALTH | Feb 13, 2024 | Feb 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2024 | Feb 13, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2024 | Feb 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 16, 2024 | Feb 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 16, 2024 | Feb 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 16, 2024 | Feb 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 16, 2024 | Feb 16, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Feb 16, 2024 | Feb 16, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 23, 2024 | Mar 6, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 29, 2024 | Feb 29, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 4, 2024 | Mar 4, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 4, 2024 | Mar 4, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 19, 2024 | Mar 26, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 25, 2024 | Mar 25, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Apr 5, 2024 | Apr 5, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 12, 2024 | Apr 19, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 17, 2024 | Apr 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 19, 2024 | Apr 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 22, 2024 | May 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 22, 2024 | May 13, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 22, 2024 | Jun 12, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 22, 2024 | Jun 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 22, 2024 | May 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 22, 2024 | May 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 22, 2024 | Jun 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 22, 2024 | Jun 4, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | May 22, 2024 | May 31, 2024 | Approved |
Public health review Public Health · HEALTH | May 22, 2024 | May 22, 2024 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2024 | Jun 4, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jun 12, 2024 | Jun 12, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2024 | Aug 1, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| Alfonso Kirkpatrick Fillon Fillon Design | Architect | C28828 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024