300 Grant Av
San Francisco permit 202311150842 · Financial District/South Beach
5th fl tenant improvement (office). generate new office, conference rooms, pantry, lounges, and bathrooms. (fire sprinkler, alarm and mep deferred)
- Filed
- Nov 15, 2023
- Issued
- Jun 13, 2024 (7 months after filing)
- Completed
- Feb 11, 2025 (8 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- Once, by Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 15, 2023 | Nov 15, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 15, 2023 | Nov 15, 2023 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Nov 15, 2023 | Nov 15, 2023 | Approved |
Public health review Public Health · HEALTH | Nov 15, 2023 | Nov 15, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 5, 2023 | Dec 5, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 10, 2024 | Jan 10, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 10, 2024 | Jan 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 11, 2024 | Jan 11, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 31, 2024 | Jan 31, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 31, 2024 | Jan 31, 2024 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2024 | Feb 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 14, 2024 | Feb 14, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 14, 2024 | Feb 14, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 14, 2024 | Feb 14, 2024 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Mar 15, 2024 | Mar 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 15, 2024 | Mar 15, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2024 | Mar 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2024 | Jun 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Hong Kook Kim Basis Engineering | Engineer | C64529 |
| Jiwon Jung Jiwon Jung | Engineer | C89281 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026