1 Helen St #0
San Francisco permit 202311150879 · Nob Hill
Construct a new 4 story, single family dwelling with attached garage
- Filed
- Nov 15, 2023
- Issued
- May 15, 2026 (30 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 38 stops across 5 departments
- Comments issued
- 14 times, by Planning, Building Inspection, Public Works, Public Utilities, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 15, 2023 | Feb 16, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 16, 2024 | Apr 3, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 16, 2024 | Jul 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 2, 2024 | Dec 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 3, 2024 | Dec 9, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 3, 2024 | Jan 22, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 3, 2024 | Dec 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 3, 2024 | Dec 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2024 | Dec 11, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 3, 2024 | Jan 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 3, 2024 | Dec 17, 2024 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 5, 2024 | Jan 3, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jan 17, 2025 | Jan 17, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jan 22, 2025 | Jan 22, 2025 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Jan 27, 2025 | Mar 4, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 25, 2025 | Feb 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 26, 2025 | Feb 26, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 3, 2025 | Mar 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 4, 2025 | Mar 4, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 28, 2025 | Apr 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 29, 2025 | Apr 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2025 | May 5, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 30, 2025 | Apr 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 14, 2025 | May 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 29, 2025 | May 29, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2025 | Jun 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2025 | Jun 5, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 5, 2025 | Jun 6, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 5, 2025 | Jun 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2025 | Jun 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2025 | Jun 10, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 5, 2025 | Jul 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2025 | Jun 10, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jun 5, 2025 | Jun 13, 2025 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Jun 10, 2025 | Jun 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 10, 2025 | Jun 10, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Jul 17, 2025 | Jul 17, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 18, 2025 | May 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,600,000
| Name | Role | License on permit |
|---|---|---|
| William David Pashelinsky William Pashelinsky | Architect | 11020 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2017