501 02nd St
San Francisco permit 202311160961 · Financial District/South Beach
Ste 600: t.i. demo full height partitions, construct new partitions, doors, millwork, mep. demising new ste 600, ste 615 and base buidling corridor.
- Filed
- Nov 16, 2023
- Issued
- Nov 30, 2023 (within 1 month of filing)
- Completed
- Feb 7, 2024 (2 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- Twice, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 16, 2023 | Nov 16, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 17, 2023 | Nov 17, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 17, 2023 | Nov 17, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 17, 2023 | Nov 17, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 17, 2023 | Nov 17, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 17, 2023 | Nov 17, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 22, 2023 | Nov 22, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 22, 2023 | Nov 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2023 | Nov 22, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 30, 2023 | Nov 30, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $539,280
| Name | Role | License on permit |
|---|---|---|
| Douglas Wayne Mehl Fennie + Mehl Architects | Architect | C17504 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026