1462 11th Av
San Francisco permit 202311201167 · Inner Sunset
941 sf vert addition of (n) 3rd flr to incl: 3 bdrms,2 baths. (n)doors, wndws & skylites. int partition chnges @ 1st & 2nd flrs. (n)2nd fl blcny & stair to rear yd. 9sf court infill 2nd fl. relocate 1st fl mech equip. full seismic upgrd of bldg. rmdl entry hall at level 1. relocate garage door.
- Filed
- Dec 1, 2023
- Issued
- Oct 29, 2024 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 53 stops across 6 departments
- Comments issued
- 9 times, by Building Inspection, Public Utilities, Fire Department, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 20, 2023 | Nov 27, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 27, 2023 | Apr 4, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 27, 2023 | Oct 15, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Feb 20, 2024 | Feb 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 4, 2024 | May 6, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 4, 2024 | Apr 11, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 4, 2024 | Apr 29, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 11, 2024 | Apr 26, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Apr 26, 2024 | Apr 26, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jun 11, 2024 | Jun 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 11, 2024 | Jul 22, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2024 | Jun 18, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 11, 2024 | Jun 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2024 | Jun 11, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 11, 2024 | Jul 1, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jul 5, 2024 | Jul 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 5, 2024 | Jul 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 5, 2024 | Jul 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 5, 2024 | Jul 8, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 5, 2024 | Jul 8, 2024 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Aug 29, 2024 | Aug 30, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 29, 2024 | Aug 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2024 | Aug 29, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 29, 2024 | Oct 3, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2024 | Sep 4, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2024 | Sep 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 3, 2024 | Oct 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2024 | Oct 29, 2024 | Administrative |
Addendum 1: Grading, foundation, steel frame & superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 5, 2024 | Nov 20, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 15, 2024 | Nov 15, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 18, 2024 | Nov 18, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Nov 20, 2024 | Nov 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 20, 2024 | Nov 21, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Jan 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2024 | Nov 25, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 21, 2024 | Jan 30, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2024 | Dec 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 29, 2025 | Jan 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2025 | Jan 31, 2025 | Administrative |
Addendum 2: Final - architectural, mechanical, t-24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2024 | Dec 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2024 | Dec 30, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 30, 2024 | Jan 24, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 30, 2024 | Feb 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 30, 2024 | Dec 31, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 30, 2024 | Jan 6, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 30, 2024 | Mar 3, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Jan 24, 2025 | Jan 24, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Jan 30, 2025 | Jan 30, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 21, 2025 | Feb 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2025 | Feb 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 21, 2025 | Feb 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 21, 2025 | Mar 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2025 | Mar 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $681,550
| Name | Role | License on permit |
|---|---|---|
| Reece Relatores Relatores Structural | Engineer | 84126 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2013