939 Castro St
San Francisco permit 202311211263 · Noe Valley
Proposed remodel with electrical, plumbing, and structural work. new 1st floor living space and new roof deck. automatic fire sprinkler only entire ground floor according with nfpa13d under deferred submittal
- Filed
- Nov 21, 2023
- Issued
- Aug 20, 2024 (9 months after filing)
- Completed
- Feb 5, 2026 (18 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 34 stops across 6 departments
- Comments issued
- 5 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 21, 2023 | Nov 21, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 21, 2023 | Nov 21, 2023 | Issued Comments |
Planning neighborhood notice Planning · CP-NP | Nov 30, 2023 | Nov 30, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 28, 2023 | Dec 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 4, 2024 | Jan 4, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 4, 2024 | Jan 4, 2024 | — |
Permit Center Permit Center · PERMIT-CTR | Feb 9, 2024 | Feb 21, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 15, 2024 | Feb 15, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 15, 2024 | Feb 15, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 22, 2024 | Feb 22, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Feb 22, 2024 | Feb 22, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 22, 2024 | Feb 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Apr 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 22, 2024 | Mar 27, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 22, 2024 | Mar 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2024 | Mar 1, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 22, 2024 | Aug 15, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2024 | Apr 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2024 | Apr 14, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 12, 2024 | Jun 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 2, 2024 | Jul 11, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 2, 2024 | Jul 8, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 2, 2024 | Jul 8, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 2, 2024 | Jul 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 2, 2024 | Jul 3, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 2, 2024 | Jul 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 16, 2024 | Jul 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 17, 2024 | Jul 17, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 17, 2024 | Aug 14, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 17, 2024 | Jul 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 17, 2024 | Jul 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 17, 2024 | Jul 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2024 | Jul 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 15, 2024 | Aug 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $366,345
| Name | Role | License on permit |
|---|---|---|
| Howard E Blecher | Architect | C36464 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2019