2732 Greenwich St
San Francisco permit 202311211273 · Marina
Renovation and addition to an existing, 3-story, 2 unit dwelling. proposed project consists of a vertical and horizontal addition, resulting in a 4-story, 2 unit building with a 2 car stacker in garage.
- Filed
- Nov 21, 2023
- Issued
- May 14, 2025 (18 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 60 stops across 6 departments
- Comments issued
- 20 times, by Planning, Building Inspection, Fire Department, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 21, 2023 | Nov 22, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 22, 2023 | Jan 27, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 22, 2023 | Mar 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 5, 2024 | Jun 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2024 | Jul 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 18, 2024 | Aug 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2024 | Jun 25, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2024 | Jul 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2024 | Aug 28, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 25, 2024 | Sep 10, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 8, 2024 | Aug 1, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2024 | Aug 28, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 29, 2024 | Aug 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 25, 2024 | Nov 4, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 25, 2024 | Sep 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2024 | Nov 15, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 25, 2024 | Nov 4, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Sep 25, 2024 | Jan 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 25, 2024 | Sep 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 12, 2024 | Dec 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 24, 2024 | Dec 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 26, 2024 | Dec 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 30, 2024 | Dec 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 31, 2024 | Dec 31, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 2, 2025 | Jan 2, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 3, 2025 | Jan 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 7, 2025 | Jan 13, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 7, 2025 | Mar 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2025 | Jan 10, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2025 | Jan 13, 2025 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Mar 5, 2025 | Mar 5, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2025 | May 14, 2025 | Administrative |
Addendum 1: Final-arch mep, super structure, foundation,t24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 15, 2025 | May 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2025 | Jul 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 22, 2025 | Jan 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 22, 2025 | Aug 24, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 22, 2025 | Aug 21, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jul 22, 2025 | Aug 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 22, 2025 | Jul 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 22, 2025 | Jul 23, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 22, 2025 | Jul 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 22, 2025 | Jul 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 22, 2025 | Jan 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Nov 3, 2025 | Nov 25, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2025 | Nov 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2025 | Nov 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2025 | Nov 13, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 12, 2025 | Dec 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2025 | Dec 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2025 | Dec 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 16, 2025 | Dec 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 24, 2025 | Dec 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 30, 2025 | Dec 31, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2025 | Dec 31, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 2, 2026 | Jan 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 5, 2026 | Jan 5, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 12, 2026 | Jan 21, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jan 21, 2026 | Jan 21, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | — | Jan 5, 2026 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,552,640
| Name | Role | License on permit |
|---|---|---|
| Geoffrey Gibson Winder Gison Architects | Architect | C35924 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022