583 Mangels Av
San Francisco permit 202311221308 · West of Twin Peaks
1/f: remove (e)garage & bathrm, create new garage, laundry rm, vestibule, bedrm, bathrm, walk-in closet, new utility area; remove (e)stairs, install new prefab spiral stairs; 2/f: remove (e)kitchen/dining room, closet, create new kitchen & closet for (e) bedroom. remodel (e) bathroom. new skylight.
- Filed
- Nov 22, 2023
- Issued
- Apr 26, 2024 (5 months after filing)
- Completed
- Feb 19, 2026 (22 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 22, 2023 | Nov 22, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 22, 2023 | Nov 22, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 22, 2023 | Nov 22, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 28, 2023 | Nov 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 28, 2023 | Nov 28, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 28, 2023 | Nov 28, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | Nov 29, 2023 | Nov 29, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2023 | Dec 29, 2023 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Dec 19, 2023 | Dec 19, 2023 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Dec 29, 2023 | Dec 29, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 29, 2023 | Mar 5, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 29, 2023 | Mar 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 4, 2024 | Apr 5, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 5, 2024 | Apr 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 12, 2024 | Apr 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 12, 2024 | Apr 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 15, 2024 | Apr 18, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 22, 2024 | Apr 24, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2024 | Apr 26, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Juan Bautista Aleman Hernandez Tangobuilder | Engineer | C86746 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025