San Francisco permit 202311221308 · West of Twin Peaks

Home remodelFull plan reviewComplete
Street view · Mar 2025
Google Street View of 583 Mangels Av, Mar 2025
Scope of work
As written on the permit application.

1/f: remove (e)garage & bathrm, create new garage, laundry rm, vestibule, bedrm, bathrm, walk-in closet, new utility area; remove (e)stairs, install new prefab spiral stairs; 2/f: remove (e)kitchen/dining room, closet, create new kitchen & closet for (e) bedroom. remodel (e) bathroom. new skylight.

Timeline
Key dates from the city record.
Filed
Nov 22, 2023
Issued
Apr 26, 2024 (5 months after filing)
Completed
Feb 19, 2026 (22 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
19 stops across 4 departments
Comments issued
4 times, by Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Nov 22, 2023Administrative

Zoning review

Planning · CP-ZOC

Nov 22, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 22, 2023Administrative

Mechanical and energy plan review

Building Inspection · MECH

Nov 28, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 28, 2023Approved

Permit Center

Permit Center · PERMIT-CTR

Nov 28, 2023—

Building pre-screening

Building Inspection · PRE-BLDG

Nov 29, 2023Issued Comments

Central Permit Bureau

Building Inspection · CPB

Dec 29, 2023Administrative

Building pre-screening

Building Inspection · PRE-BLDG

Dec 19, 2023Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Dec 29, 2023Approved

Building plan review

Building Inspection · BLDG

Mar 5, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 8, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Apr 5, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 11, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 12, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 15, 2024Approved

Zoning review

Planning · CP-ZOC

Apr 18, 2024Approved

Permit Processing Center

Building Inspection · PPC

Apr 24, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 26, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$250,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Juan Bautista Aleman Hernandez

Tangobuilder

EngineerC86746
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202311221308 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record