301 King St #0
San Francisco permit 202311271435 · Mission Bay
Conversion of un-used parking spots on the 2nd & 3rd floor into 10 new accessory dwelling units (adus) with (n) kitchen, bedroom, living room and new bathroom
- Filed
- Nov 27, 2023
- Issued
- Jul 30, 2026 (32 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 44 stops across 7 departments
- Comments issued
- 9 times, by CON, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 27, 2023 | Nov 30, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Nov 28, 2023 | Jul 10, 2026 | Administrative |
CON CON-BOND | Dec 4, 2023 | Dec 4, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 4, 2023 | Dec 19, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 4, 2023 | Jan 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2023 | Dec 21, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 4, 2023 | Dec 6, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2023 | Dec 5, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 4, 2023 | Jul 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2023 | Dec 5, 2023 | Approved |
Redevelopment review Redevelopment · REDEV | Dec 27, 2023 | Feb 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 13, 2024 | May 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2024 | Jun 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2024 | May 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 10, 2024 | Jun 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 30, 2024 | Oct 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 28, 2024 | Oct 28, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 28, 2024 | Oct 28, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 30, 2024 | Oct 31, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 30, 2025 | Jul 7, 2025 | Approved |
Redevelopment review Redevelopment · REDEV | Jul 1, 2025 | Jul 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2025 | Jul 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 1, 2025 | Jul 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2025 | Jul 1, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Jul 8, 2025 | May 27, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 24, 2026 | Apr 28, 2026 | Approved |
Redevelopment review Redevelopment · REDEV | Apr 27, 2026 | May 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 27, 2026 | May 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 27, 2026 | Apr 28, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 27, 2026 | Apr 28, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 27, 2026 | May 6, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 27, 2026 | May 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 27, 2026 | Apr 28, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 8, 2026 | Jun 9, 2026 | Issued Comments |
Redevelopment review Redevelopment · REDEV | Jun 26, 2026 | Jun 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 26, 2026 | Jun 26, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 26, 2026 | Jun 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 26, 2026 | Jun 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 26, 2026 | Jul 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2026 | Jul 1, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 26, 2026 | Jul 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 26, 2026 | Jun 29, 2026 | Approved |
CON CON-BOND | Jul 8, 2026 | Jul 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2026 | Jul 30, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,260,844
| Name | Role | License on permit |
|---|---|---|
| Christopher J Dorman Dorman Assoc | Architect | C28300 |
| Matthew Palmer Frantz Zfa Structural Engineers | Engineer | 5919 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026