CheckMyDesigner

301 King St #0

San Francisco permit 202311271435 · Mission Bay

ADUFull plan reviewIssued
Street view · Sep 2026
Google Street View of 301 King St #0, Sep 2026
Scope of work
As written on the permit application.

Conversion of un-used parking spots on the 2nd & 3rd floor into 10 new accessory dwelling units (adus) with (n) kitchen, bedroom, living room and new bathroom

Timeline
Key dates from the city record.
Filed
Nov 27, 2023
Issued
Jul 30, 2026 (32 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
44 stops across 7 departments
Comments issued
9 times, by CON, Building Inspection, Fire Department
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 30, 2023Administrative

Permit Processing Center

Building Inspection · PPC

Jul 10, 2026Administrative

CON

CON-BOND

Dec 4, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Dec 19, 2023Administrative

Building plan review

Building Inspection · BLDG

Jan 26, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 21, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 6, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 5, 2023Approved

Urban forestry

Public Works · DPW-BUF

Jul 4, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 5, 2023Approved

Redevelopment review

Redevelopment · REDEV

Feb 27, 2024Approved

Fire prevention review

Fire Department · SFFD

May 15, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 13, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 30, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 10, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 17, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Oct 28, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 28, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 31, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 7, 2025Approved

Redevelopment review

Redevelopment · REDEV

Jul 7, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 3, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 2, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 1, 2025Approved

Development fee collection

Building Inspection · DFCU

May 27, 2026Administrative

Fire prevention review

Fire Department · SFFD

Apr 28, 2026Approved

Redevelopment review

Redevelopment · REDEV

May 1, 2026Approved

Building plan review

Building Inspection · BLDG

May 26, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 28, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 28, 2026Approved

Street use and mapping

Public Works · DPW-BSM

May 6, 2026Approved

Urban forestry

Public Works · DPW-BUF

May 17, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 28, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 9, 2026Issued Comments

Redevelopment review

Redevelopment · REDEV

Jun 30, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 26, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 30, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 30, 2026Approved

Fire prevention review

Fire Department · SFFD

Jul 9, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jul 1, 2026Approved

Urban forestry

Public Works · DPW-BUF

Jul 2, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 29, 2026Approved

CON

CON-BOND

Jul 8, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jul 30, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,260,844
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Christopher J Dorman

Dorman Assoc

ArchitectC28300
Matthew Palmer Frantz

Zfa Structural Engineers

Engineer5919
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202311271435 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record