159 Fell St
San Francisco permit 202311281457 · Hayes Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Alter site permit to pa 201912200114s. eliminate basement & move utility spaces to the ground fl. eliminate retail space at ground fl & provide one additional residential unit for a total of 25. fell & hickory ground fl street facades revised to show changes in use. no changes to fl 2-7.
- Filed
- Nov 28, 2023
- Issued
- Jul 16, 2024 (8 months after filing)
- Completed
- Not completed yet
- Review stops
- 104 stops across 7 departments
- Comments issued
- 28 times, by Building Inspection, Public Utilities, Fire Department
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 28, 2023 | Nov 28, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 30, 2023 | Nov 30, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 30, 2023 | Nov 30, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Dec 22, 2023 | Dec 22, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 31, 2024 | Feb 8, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 5, 2024 | Feb 5, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Feb 8, 2024 | Feb 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 9, 2024 | Feb 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 13, 2024 | Feb 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2024 | Mar 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2024 | Mar 29, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2024 | Feb 20, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 13, 2024 | Jun 3, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 14, 2024 | Feb 27, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 15, 2024 | Mar 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2024 | Mar 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 16, 2024 | Apr 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 16, 2024 | Apr 30, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 16, 2024 | May 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2024 | Apr 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2024 | Apr 17, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2024 | Apr 24, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 26, 2024 | Apr 26, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 2, 2024 | May 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 2, 2024 | May 17, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | May 2, 2024 | May 21, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | May 2, 2024 | May 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 2, 2024 | May 6, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 2, 2024 | May 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2024 | Jul 16, 2024 | Administrative |
Addendum 1: Foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 31, 2024 | Aug 13, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 5, 2024 | Aug 5, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 7, 2024 | Aug 7, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Aug 12, 2024 | Aug 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2024 | Aug 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 15, 2024 | Sep 11, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2024 | Aug 21, 2024 | Approved |
Public health review Public Health · HEALTH | Aug 15, 2024 | Sep 17, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Aug 15, 2024 | Nov 18, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 13, 2024 | Oct 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2024 | Sep 18, 2024 | Approved |
Public Health HEALTH-MH | Sep 17, 2024 | Sep 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 18, 2024 | Nov 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 18, 2024 | Oct 23, 2024 | Approved |
Public health review Public Health · HEALTH | Oct 18, 2024 | Oct 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 1, 2024 | Nov 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2024 | Nov 13, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Apr 10, 2025 | Sep 9, 2025 | Administrative |
Addendum 2: Architectural mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 5, 2024 | Aug 5, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 7, 2024 | Aug 7, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 8, 2024 | Aug 8, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Dec 13, 2024 | Dec 27, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 7, 2025 | Jan 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 8, 2025 | Jan 8, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Jan 8, 2025 | Oct 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 9, 2025 | Jan 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2025 | Jan 27, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2025 | Jan 28, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 9, 2025 | Jan 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 9, 2025 | Jan 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2025 | Jan 23, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 9, 2025 | Apr 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2025 | Jan 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 9, 2025 | May 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 9, 2025 | Jun 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 9, 2025 | Jun 16, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 9, 2025 | May 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 9, 2025 | May 13, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 9, 2025 | May 19, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 9, 2025 | Jun 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2025 | Jun 4, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 8, 2025 | Aug 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Aug 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2025 | Aug 20, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 8, 2025 | Aug 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 8, 2025 | Aug 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2025 | Aug 21, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 8, 2025 | Aug 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 8, 2025 | Aug 8, 2025 | Approved |
Building Inspection MECH-E-QC | Aug 29, 2025 | Aug 29, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 12, 2025 | Sep 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 12, 2025 | Sep 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 12, 2025 | Oct 1, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 12, 2025 | Sep 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 12, 2025 | Sep 16, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2025 | Sep 15, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 12, 2025 | Sep 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 12, 2025 | Sep 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 29, 2025 | Sep 29, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 8, 2025 | Oct 8, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 8, 2025 | Oct 8, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 10, 2025 | Oct 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2025 | Oct 29, 2025 | Administrative |
Addendum 3: Fire sprinklers & underground
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 11, 2026 | Feb 26, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2026 | Mar 5, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 5, 2026 | Mar 7, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 5, 2026 | May 1, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 28, 2026 | Apr 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 1, 2026 | May 4, 2026 | Administrative |
Addendum 5: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 27, 2025 | Jul 1, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2025 | Jul 1, 2025 | Administrative |
Public Health HEALTH-MH | Jul 2, 2025 | Jul 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 2, 2025 | Jul 3, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2025 | Sep 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,278,000
| Name | Role | License on permit |
|---|---|---|
| Geoffrey Gibson Winder Gison Architects | Architect | C35924 |
| Donald David Double D Engineering | Engineer | S-3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026