151 Warriors Wy
San Francisco permit 202311281506 · Mission Bay
Suite 105-106: first time t.i. of existing commercial retail/food shell. install new kitchen & food service equipment, appliances, and other needed elements. new flooring, lighting, elegant finishes. life safety under separate permit
- Filed
- Nov 28, 2023
- Issued
- May 28, 2024 (6 months after filing)
- Completed
- Oct 30, 2024 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Nov 28, 2023 | Nov 28, 2023 | Approved |
Intake Building Inspection · INTAKE | Nov 28, 2023 | Nov 28, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 30, 2023 | Nov 30, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 30, 2023 | Nov 30, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 15, 2023 | Dec 15, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Dec 15, 2023 | Dec 15, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 22, 2023 | Dec 22, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Dec 22, 2023 | Dec 22, 2023 | Administrative |
Public health food review Public Health · HEALTH-FD | Dec 22, 2023 | Dec 27, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 3, 2024 | Jan 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 26, 2024 | Jan 26, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 26, 2024 | Jan 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2024 | Jan 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 29, 2024 | Jan 29, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2024 | Jan 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 15, 2024 | Feb 15, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 23, 2024 | Feb 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 27, 2024 | Feb 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2024 | Feb 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 27, 2024 | Feb 27, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2024 | Feb 27, 2024 | Approved |
Public health food review Public Health · HEALTH-FD | Feb 27, 2024 | Mar 1, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 7, 2024 | Mar 7, 2024 | Approved |
Redevelopment review Redevelopment · REDEV | Mar 12, 2024 | Mar 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 28, 2024 | May 28, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $2,250,000
| Name | Role | License on permit |
|---|---|---|
| Jay Sherlock Studio J. Architecture | Architect | C33354 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2020