60 Spear St
San Francisco permit 202311281534 · Financial District/South Beach
Demo & repaving of (e) parking for new waterproofing/repair, restriping of parking stalls/aisles to match (e), selective demo of basement walls, ceilings, mep elements, waterproofing associated w/parking, north passage drain, leaks asso w/(e) piping, & (e) structure where necessary, new min req emer
- Filed
- Nov 28, 2023
- Issued
- Dec 22, 2023 (within 1 month of filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 14 stops across 4 departments
- Comments issued
- Twice, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Plumbing inspector Building Inspection · PID-INSP | Nov 28, 2023 | Nov 28, 2023 | Approved |
Intake Building Inspection · INTAKE | Nov 28, 2023 | Nov 28, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Nov 28, 2023 | Nov 28, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Nov 29, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 29, 2023 | Nov 29, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 30, 2023 | Nov 30, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 30, 2023 | Nov 30, 2023 | Issued Comments |
Intake Building Inspection · INTAKE | Dec 6, 2023 | Dec 6, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 6, 2023 | Dec 6, 2023 | Approved |
Intake Building Inspection · INTAKE | Dec 12, 2023 | Dec 12, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 12, 2023 | Dec 12, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Dec 19, 2023 | Dec 19, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2023 | Dec 20, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 22, 2023 | Dec 22, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $75,050
| Name | Role | License on permit |
|---|---|---|
| Guion Cabell Childress | Architect | C39053 |
| Joseph Kenneth Young Bkf | Architect | C84619 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026