353 King St
San Francisco permit 202311291555 · Mission Bay
Conversion of (e) social lounge into (n) 1 bedroom adu unit on the 3rd floor accessory dwelling units (adus) with (n) kitchen, bedroom, living room and bathroom @ 353/383 king st.
- Filed
- Nov 29, 2023
- Issued
- Aug 7, 2024 (8 months after filing)
- Completed
- Jan 8, 2025 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 23 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 29, 2023 | Dec 6, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 6, 2023 | Dec 11, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 6, 2023 | Jan 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 6, 2023 | Jan 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 6, 2023 | Jan 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2023 | Dec 12, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 6, 2023 | Apr 27, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 6, 2023 | Dec 8, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 6, 2023 | May 9, 2024 | Administrative |
Redevelopment review Redevelopment · REDEV | Dec 11, 2023 | Feb 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 22, 2024 | Feb 26, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Feb 27, 2024 | Mar 4, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2024 | Feb 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 27, 2024 | Apr 2, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2024 | Mar 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2024 | Mar 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 21, 2024 | Mar 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2024 | Apr 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 19, 2024 | Apr 19, 2024 | Approved |
Redevelopment review Redevelopment · REDEV | Apr 29, 2024 | May 1, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | May 2, 2024 | May 9, 2024 | Approved |
Development fee collection Building Inspection · DFCU | May 2, 2024 | May 2, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 9, 2024 | Aug 7, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $213,104
| Name | Role | License on permit |
|---|---|---|
| Christopher J Dorman Dorman Assoc | Architect | C28300 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026