San Francisco permit 202311291555 · Mission Bay

ADUFull plan reviewComplete
Street view · Sep 2026
Google Street View of 353 King St, Sep 2026
Scope of work
As written on the permit application.

Conversion of (e) social lounge into (n) 1 bedroom adu unit on the 3rd floor accessory dwelling units (adus) with (n) kitchen, bedroom, living room and bathroom @ 353/383 king st.

Timeline
Key dates from the city record.
Filed
Nov 29, 2023
Issued
Aug 7, 2024 (8 months after filing)
Completed
Jan 8, 2025 (5 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 6 departments
Comments issued
4 times, by Building Inspection, Fire Department
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 6, 2023Administrative

Zoning review

Planning · CP-ZOC

Dec 11, 2023Administrative

Building plan review

Building Inspection · BLDG

Jan 19, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 5, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 30, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 12, 2023Approved

Urban forestry

Public Works · DPW-BUF

Apr 27, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 8, 2023Approved

Permit Processing Center

Building Inspection · PPC

May 9, 2024Administrative

Redevelopment review

Redevelopment · REDEV

Feb 27, 2024Approved

Fire prevention review

Fire Department · SFFD

Feb 26, 2024Approved-Stipulated

Building plan review

Building Inspection · BLDG

Mar 4, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 29, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 2, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 15, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 1, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 21, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 19, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 19, 2024Approved

Redevelopment review

Redevelopment · REDEV

May 1, 2024Approved

Urban forestry

Public Works · DPW-BUF

May 9, 2024Approved

Development fee collection

Building Inspection · DFCU

May 2, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 7, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$213,104
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Christopher J Dorman

Dorman Assoc

ArchitectC28300
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202311291555 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record